In June 2020 Didostati LLC has carries out the Drilling Pile Load Test - five units of drilling piles were arranged by Didostati LLC. The company has carried out the following services: drilling; fabricating the rainforcement cages; installing the rainforcement cages; concrete pouring. After fulfilling the drilling pile arrangements the load was applied by means of electrical hydraulic pump and the test load was applied as per below cycles:

Cycle 1:

Pile No. Nominal pile Dia. (mm) Working Load (kN)
T01 1200 13000  kN

 

Cycle 2:

Pile No. Nominal pile Dia. (mm) Working Load (kN)
T01 1200 26000  kN

 

The test program was carried out in 26.58 hours (net 24.83 hours) and has become one more success for the company!

 

This experience was not the first for the comany and has once more approved  that Didostati LLC guarantees the quality of its services!